logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 부산지방법원동부지원 2017.11.24 2016가합101883
공사대금등
Text

1. Defendant C Co., Ltd.: (a) KRW 110,652,280 to Plaintiff Co., Ltd.; and (b) from June 4, 2016 to November 24, 2017.

Reasons

1. Facts of recognition;

A. The relationship between the parties 1) Defendant C Co., Ltd. (hereinafter “Defendant C”).

)은 토목건축공사업, 주택건설업 등을 위해 1988. 11. 30. 설립된 회사이고, 주식회사 A(이하 ‘원고 A’라고 한다

(2) Defendant D was registered as the representative director of each Defendant C during the period from August 26, 199 to March 25, 2002; from January 3, 2002 to August 26, 2002; from January 16, 2003 to April 15, 2010; from July 14, 201 to December 30, 201, Defendant C was registered as the representative director of each Defendant C during the period from January 24, 2012; and Defendant C had taken office as the representative director of each Defendant C on December 24, 2015; and Defendant C had taken office as the representative director of each Defendant C on May 1, 2016.

On the other hand, Plaintiff B was registered as Defendant C’s representative director from January 2, 2012 to April 29, 2016.

3) On April 1, 2014, Plaintiff B was registered as Plaintiff A’s intra-company director. Plaintiff B’s ASEAN was registered as Plaintiff B’s representative director from April 1, 2014 to September 21, 2015, Plaintiff B’s ASEAN was registered as Plaintiff A’s representative director from September 21, 2015 to March 28, 2016, and the F was reappointed as Plaintiff A’s representative director on June 1, 2016. (b) Defendant C was awarded a contract for H Corporation (hereinafter “H Corporation”) from the Daegu-gu Busan Metropolitan Government Maritime Transportation Authority around 2014 to KRW 1,779,571,000.

On May 30, 2014, Defendant C entered into a subcontract with the Plaintiff on May 30, 2014, setting the construction period of reinforced concrete construction works among H construction works as KRW 1,150,000 (the construction price of July 31, 2015 changed to KRW 1,265,879,000).

2) Defendant C is the I Corporation from the North-gu Busan Metropolitan Government Office (hereinafter “I Corporation”) around 2014.

D) Defendant C was awarded a contract with the Plaintiff for KRW 1,791,070,000 on July 18, 2014, for construction period of reinforced concrete construction works among the I construction works, from July 18, 2014 to August 19, 2015, and for construction cost of KRW 1,001,50,000 (hereinafter “the construction period”).

arrow