Text
1. The Defendant’s KRW 126,435,918 among the Plaintiff and KRW 75,001,488 among the Plaintiff, shall be KRW 51,434,430 from October 21, 2015.
Reasons
1. Basic facts
A. On March 5, 2012, A Co., Ltd. (hereinafter “Rehabilitation Company”) concluded a contract for construction work in the form of a long-term continuing construction contract (hereinafter “instant contract”) with the Defendant for a long-term continuing construction contract (hereinafter “long-term continuing construction contract”) with a total construction period of KRW 3,395,652,00, and a total construction period of KRW 3,395,652,000 with respect to the instant construction work (hereinafter “instant construction work”) from March 12, 2012 to August 28, 2014. The rate of liquidated damages was 0.1% of the daily allowance for the contract amount (annual contract amount of long-term continuing construction contract).
(2) The rehabilitation company and the Defendant concluded the instant contract by dividing the two-lanes, and concluded the instant contract by multiple times on the grounds of construction completion delay, design change, etc., and concluded a contract to amend the instant contract and the instant contract by multiple times, thereby reducing the final total construction period by KRW 3,101,250,000, and extended the completion date of the total construction period by March 1, 2015.
The main contents of each revised contract shall be as follows:
구분 변경 횟수 계약일 계약금액(단위: 원) 착공일 준공일 공사기간 증감 총괄 최초 2012. 3. 5. 3,395,652,000 2012. 3. 12. 2014. 8. 28. 1회 2013. 7. 30. 3,395,652,000 2014. 10. 28. 61일 2회 2013. 9. 10. 3,221,212,000 2014. 10. 28. 3회 2014. 5. 11. 3,221,212,000 2014. 12. 28. 61일 4회 2014. 12. 23. 3,101,250,000 2014. 12. 28. 5회 2015. 2. 25. 3,101,250,000 2015. 3. 1. 63일 1차 최초 2012. 3. 8. 1,430,370,000 2012. 3. 12. 2013. 6. 4. 1회 2013. 7. 27. 1,430,370,000 2013. 9. 18. 106일 2회 2013. 9. 10. 1,255,930,000 2014. 10. 28. 511일 2차 최초 2013. 1. 15. 1,965,282,000 2013. 1. 18. 2014. 8. 28. 1회 2013. 7. 30. 1,965,282,000 2014. 10. 28. 61일 2회 2014. 5. 11. 1,965,282,000 2014. 12. 28. 61일 3회 2014. 12. 23. 1,845,320,000 2014. 12. 28. 4회 2015. 2. 25. 1,845,320,000 2015. 3. 1. 63일 (3) 이후 회생회사는 2014. 12. 15. 피고와 사이에 추가로 D 정비공사(총괄) 이하 ’D 공사‘라고...