logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2014.10.23 2014가합567010
구상금
Text

1. The defendant shall pay to the plaintiff KRW 139,558,660 as well as to the day of full payment from the day following the day when this judgment becomes final and conclusive to the day of full payment.

Reasons

1. Facts of recognition;

(a) Claim A of the Credit Guarantee Fund 1) The Credit Guarantee Fund shall be a stock company D (hereinafter referred to as “D”) as listed in the following table:

(1) In the aggregate of the credit guarantee agreements with a credit guarantee agreement (hereinafter referred to as "credit guarantee agreement of this case"), the credit guarantee agreement of this case shall be

(2) A. (3) Until March 21, 2011, the Korea Credit Guarantee Fund concluded a credit guarantee agreement under Article 2 (2) of the Credit Guarantee Agreement (amended by March 21, 2012) on the date of the Credit Guarantee Agreement (amended by 202,50,000 won) for the creditor-guaranteed principal of the creditor-guaranteed principal of the Credit Guarantee Agreement until March 22, 2011 (amended by 202,50,000 won) until April 13, 2012 (amended by 45,00,000,000 won for the new bank until April 13, 2012) is to bear the debt guarantee agreement under Article 3 (2) of the Credit Guarantee Agreement until April 13, 2011 (Amended by 297,000,0000,0000 won for the creditor-guaranteed principal of the Credit Guarantee Fund until April 13, 2013.

3) D submits each credit guarantee form issued pursuant to the instant credit guarantee agreement and a new bank (hereinafter “new bank”) which is a stock company.

From 250,000,000 won (the first credit guarantee agreement), 50,000,000 won (the second credit guarantee agreement), 330,000,000 won (the third credit guarantee agreement), and the Industrial Bank of Korea (the “Corporate Bank”) (the third credit guarantee agreement)

D) Upon entering into the instant credit guarantee agreement, D) concluded an agreement with the Credit Guarantee Fund to pay the amount of damages for delay calculated at the rate of 12% per annum as determined by the Credit Guarantee Fund, within the limit of 25% per annum as stipulated by the Credit Guarantee Fund from the date of subrogation to the date of full payment, when the Credit Guarantee Fund performs a guaranteed obligation under the credit guarantee agreement.

5 The Credit Guarantee Fund shall be from the New Bank on October 17, 2012 and from the Enterprise Bank on October 18, 2012, respectively.

arrow