Text
1. The Defendant’s KRW 1,00,000,000 for the Plaintiff and 5% per annum from October 20, 2016 to August 30, 2017.
Reasons
1. Facts of recognition;
A. The Plaintiff is an organization formed by the residents of the Gyeong-gun, Gyeong-gun, Gyeong-gun, Gyeong-gun, and the 4-Jeng village with respect to the construction of wind power plants in the Han-do, Hansan-gun, and the Defendant is a company established for the purpose of constructing wind power generation complexes in the Gyeong-gun, Gyeongnam-gun.
1. For wind power generation with the regional development fund, 1.3 billion won shall be applied to the residents' countermeasures;
2. The point of time of support shall be 300 million won within 21 days after signing a written agreement and the balance within 30 days after the inspection before the use of the development complex is completed.
5. Residents' Countermeasure Committee shall endeavor to fully cooperate for the smooth progress of works during the construction period.
B. On November 16, 2015, the Defendant promoted a project to build a wind power generation complex on the ground level 203 and 26 lots of land, Gyeong-gun, Gyeong-gun, Gyeong-gun, Gyeong-gun, and agreed with the Plaintiff as follows.
C. On December 21, 2015, the Defendant paid KRW 300 million out of the subsidies 1.3 billion agreed upon under the above agreement to the Plaintiff, and the remainder of KRW 1 billion was not paid up to the present day.
On September 19, 2016, the defendant was notified of construction completion with respect to construction works for the wind power generation complex.
【Facts without dispute over the grounds for recognition, entry of Gap's evidence 1 through 4, purport of the whole pleadings
2. According to the above facts of recognition, the Defendant is obligated to pay the Plaintiff the amount of KRW 1 billion payable according to the above agreement and the damages for delay calculated at the rate of 5% per annum as stipulated in the Civil Act until August 30, 2017, which is the date of this decision, as the Plaintiff seeks from October 20, 2016, after the lapse of 30 days from September 19, 2016, from the date when the Defendant received notice of completion from the Ma-gun on September 19, 2016, which is the date of this decision, and as the Defendant seeks, from October 20, 2016.
3. In conclusion, the plaintiff's claim of this case is reasonable, and it is so decided as per Disposition.