(영문) 울산지방법원 2016.12.14 2016가합1508
광산갱도 출입금지
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

The relationship C between the parties on the basis was registered with the establishment of the mining right (hereinafter referred to as “the mining right of this case”) on the F whole unit of the mining concession in Ulsan-gun, Ulsan-gun and E on May 14, 1982 (area: 279h, name of mineral species: modified: the duration of the mining right from May 15, 1982 to April 30, 2007; registration number G) and with the authorization of the mining plan on July 3, 1982.

The mining right of this case is currently owned jointly by the plaintiff, social welfare foundation H, and I, each of 1/3 shares through multiple changes of owners, and the plaintiff is its representative.

The plaintiff applied for the extension registration of the term of the mining right of this case on January 8, 2007 with respect to the extension permission of the term of the mining right of this case on January 1, 2007, and upon such application, the term of the mining right of this case was extended from May 1, 2007 to April 30, 2027.

On November 11, 1986, C, including the Defendant’s mine possession, established the Defendant (J Co., Ltd.) on November 11, 1986, and the real estate listed in the attached list (hereinafter “instant land”) was determined as tourism and recreation area under the Act on the Utilization and Management of the National Territory on September 2, 1986, the construction of a tourist resort development project was commenced after obtaining approval from the Minister of Construction and Transportation on June 26, 1987 for a comprehensive plan for a tourist resort development project for a tourist resort development project after obtaining permission from the Minister of Construction and Transportation on June 26, 1987, among three mines located under the ground of the instant land formed and expanded by a self-revision mining work (hereinafter “the instant mine”). From the beginning of 1998, C, with the mutual name “K”, collects from many unspecified and unspecified persons, such as dump pit, dump, permanent performance theater, ice, and admission fees.

Nos. 5, 6, and 1-1 through 3 of the Evidence Nos. 5, 6, and 1-3 of the above Act. The defendant is the Ulsan District Court No. 2966, Feb. 19, 2016, which was received on February 19, 2016.