(영문) 대구지방법원 서부지원 2018.08.22 2014가단31879
공사대금등
Text

1. Defendant B Co., Ltd.: 31,00,000 won and 5% per annum from October 29, 2014 to August 22, 2018.

Reasons

1. Basic facts

A. The Plaintiff is a person who engages in household management with the trade name “D(E)”.

Defendant B Co., Ltd. (hereinafter “Defendant B”) is a construction company that received a contract from the F Co., Ltd. (hereinafter “F”) for the new construction of the G building in Chungcheongnam-do (hereinafter “instant new construction”). Defendant C is the head of the field office of Defendant B.

B. On June 24, 2014, the Plaintiff entered into a standard contract for the entrustment of the manufacture of construction materials (hereinafter “instant contract”) with Defendant B with the main household and general household supply construction among the instant new construction works (hereinafter “instant subcontracted construction”) with the construction cost of KRW 159,720,00 (including value-added tax). The details of the instant contract are as follows.

Standard contract for the manufacture entrustment of construction materials

2. Name of the construction work of new building: Contract price of construction work to be installed in the main household and general household supply: 159,720,000 won (including value-added tax): Contract price for delay: 1/1,000 of the contract price: From July 1, 2014 to September 4, 2014: Contract price for the period of guarantee: Article 12 of the General Conditions for the Contract for the Contract for the Manufacture of Construction Materials: Contract Price for 10% of the contract price for the construction work: (1) The Party A shall pay the price for supply within the period set by the short period of 90 days from the date of receipt of the object.

(2) Where the date of payment is not determined, the sixty days after the object is received, shall be deemed the payment date of the price.

Article 16 [Compensation for Delay] (1) When Eul fails to deliver any goods within the delivery period stipulated in the contract, it shall pay Gap in cash the amount calculated by multiplying the contract amount by 1/1,000 of the contract amount for each number of days of delay.

C. In order to implement the instant contract, the Plaintiff is with H (I) around July 2014, as the price of 36,000,000 won (e.g., hybrids, graphites, and Blacks, and with J (K) for the Han announcementm and cremations, and L corporation.