(영문) 수원지방법원 2016.08.16 2014가합13443
양수금
Text

1. The Defendant’s KRW 43,559,00 for the Plaintiff and KRW 5% per annum from November 12, 2014 to August 16, 2016.

Reasons

Facts of recognition

C On September 30, 2013, the Defendant entered into a contract with the Defendant for the construction of a new building listed in the separate sheet (hereinafter “instant building”) (hereinafter “instant construction”). The main contents of the said contract are as follows.

The total construction cost under paragraph (1) shall be KRW 520,00,000 (Provided, That the penalty tax shall be separately imposed), and the payment of the construction cost shall be made in accordance with the progress rate of official approval.

(1) The warranty period of Paragraph (3) shall be one year after the completion of the building, and the warranty of defects shall be replaced by the warranty bond of KRW 5 million out of the construction cost, and the payment of deposit shall be made at the time of completion, prompt measures shall be taken for the defective parts and necessary matters shall be handled with the confirmation of the owner of the building.

(1) The payment of construction expenses under paragraph (5) (1) : 30,000,000 won for the first half: 50,000 won for the second half payment (2) (3) : 50,000,000 won for the second half payment (3) (3) : 50,000,000 won for the second half payment (20,000 won for the second half payment at the time when the structural frame of the third floor is completed, October 203): 10,00 won for the third half payment (80,000,000 won at the fair rate of 80,000, and December 11, 2013): 20,00 won for the fourth payment (6) : 150,000,000 won for the fifth half payment: 150,000 won for the second half payment at the construction expense; 10,000 won for the remainder of the lease deposit (excluding the remainder of 28,20,2014).

The construction schedule referred to in paragraph (6) shall begin on October 1, 2013 and begin on February 25, 2014, be the completion date of the construction project.

Provided, That the date of completion of construction shall be February 15, 2014, except for the delay of construction due to bad weather conditions and natural disasters.

The compensation rate for delay of construction under paragraph (7) shall be an amount calculated by multiplying the total construction cost per day by 1/1000, and the compensation rate for delay of construction cost shall be the same amount as the total construction cost per day multiplied by 1/1000.

Under special agreement, air-conditioning units for the main living room for the main household, studio 2 (studio), and air-conditioning units for the studio 2 households shall be installed at the cost of Grade C.

The defendant.