(영문) 서울동부지방법원 2018.07.24 2018가단117204
대여금
Text

1. The Defendant’s KRW 50,000,000 and the Plaintiff’s annual rate of KRW 5% from December 1, 2009 to April 29, 2018.

Reasons

1. According to Gap evidence Nos. 1 through 4, the plaintiff is obligated to pay to the plaintiff 50,000,000 won a sum of the 50,000,000 won from November 30, 2006 to November 18, 2008 as the due date for repayment. Thus, the defendant is obligated to pay to the plaintiff 50,000,000 won a loan and damages for delay calculated at each rate of 15% per annum as prescribed by the Civil Act from December 1, 2009 to April 29, 2018, the delivery date of a copy of the complaint of this case from December 1, 2009 to April 29, 2018.

2. The plaintiff's claim for conclusion is reasonable, and it is so decided as per Disposition.