(영문) 수원지방법원 2017.11.02 2015가단59432
양수금
Text

1. The defendant shall be the plaintiff.

(a) KRW 45,237,106 and KRW 4,778,630 among them shall be from January 1, 2013; KRW 8,010,00.

Reasons

1. Basic facts

A. Korea Housing Construction Co., Ltd. (hereinafter “Korea Housing Construction”) and Korea Housing Guarantee Co., Ltd. (hereinafter “Korea Housing Construction”)

Korea Housing Guarantee Co., Ltd. (hereinafter “Korea Housing Guarantee”) on November 29, 2006

(b)BB and 26 parcels of land owned by Hanwon Construction Co., Ltd. (including the transfer of ownership on land or housing), if it is impracticable for Hanwon Construction Co., Ltd to carry out the sales contract, or if Hanwon Construction Co., Ltd. is unable to carry out the sales contract, the sale contract shall be executed to the buyer, or if Hanwon Construction Co., Ltd., the sale contract shall be executed to the buyer, the sale contract shall be executed to the buyer;

hereinafter the same shall apply.

(2) On November 29, 2006, the Korea Housing Guarantee Co., Ltd. issued a house sale guarantee certificate to the Korea Housing Construction Co., Ltd. on November 29, 2006, and the ownership transfer registration was completed in the name of the Korea Housing Guarantee Co., Ltd. for the said land.

B. On March 31, 2009, the date of completion of the initial completion plan for the apartment as to the above apartment, the approval for use was granted on January 22, 2010. 2) On January 15, 2010, some of the buyers of the above apartment units were entitled to claim the return of the sale price due to the cancellation of the sale contract when the new construction was delayed, and on September 15, 2009, the registration of preservation of ownership was completed on the provisional attachment order (Seoul Central District Court Decision 2009Kadan6950, 2009Kadan7030) based on the provisional attachment order (Seoul Central District Court Decision 2009Kadan6950, 2009Kadan7030), and thereafter the provisional attachment entry registration was completed.

(C) On February 26, 2010, Korea Housing Guarantee Co. 3, 2000, upon the provisional attachment and application of the above auction by the buyers, the said apartment.

arrow