Text
1. The Defendant’s KRW 68,00,000 as well as the Plaintiff’s annual rate of 5% from April 24, 2015 to September 1, 2016, and the following.
Reasons
1. Basic facts
A. The Plaintiff (from B to September 19, 2014) is a company with the purpose of manufacturing automobile parts, etc., and the Defendant is a company with the purpose of manufacturing and selling heavy equipment parts.
B. On March 19, 2014, the Defendant sold the purchase price of KRW 5,280,000 for KRW 650,000,00 for KRW 4,630,000 for the remainder of KRW 4,630,000,00 without intermediate payment, to the Plaintiff on September 2, 2014, the Plaintiff agreed to deliver the instant real estate on August 31, 2014, by selling KRW 3,31,311,300 square meters of a member-gu Seoul Factory Site and its ground building, and the aggregate of the above land and buildings (hereinafter collectively referred to as “instant real estate”).
(hereinafter referred to as “first sale contract”). (c)
Pursuant to the first sale contract, the Plaintiff agreed with the Defendant to pay the Defendant the sum of KRW 200,000,000 as the down payment on March 19, 2014, KRW 200,00 on March 20, 2014; KRW 50,000,000 on March 26, 2014; and KRW 20,000 on March 28, 2014; and KRW 550,000,000 on June 20, 2014; and the remainder of KRW 100,000,000 on June 30, 2014 as the remainder payment.
Meanwhile, in order to use the instant real estate as the Plaintiff’s factory and office until the delivery thereof, the Plaintiff leased the lease deposit of KRW 300,000,000,000, monthly rent of KRW 20,000,000, and the lease period from May 30, 2014 to September 30, 2014, with the aim of using it as the Plaintiff’s factory and office.
(hereinafter referred to as “the first lease contract”). (e)
However, on August 31, 2014, the Defendant requested the Plaintiff to late the delivery date of the instant real estate. Accordingly, on September 2, 2014, the Plaintiff: (a) leased a factory building among the instant real estate to the Defendant, with the lease deposit of KRW 280,00,000; (b) the rent of KRW 15,00,000,000; and (c) the lease period from September 2, 2014 to November 1, 2014; (d) the lease period may be changed by mutual consultation; and (e) the rent may be changed by October 1, 2014.