Text
1. The Defendant shall pay to the Plaintiff KRW 27,50,000 and the interest rate of KRW 15% per annum from May 29, 2018 to the day of complete payment.
Reasons
1. Comprehensively taking account of the overall purport of Gap evidence Nos. 1 through 3 as to the cause of the claim and the entire arguments, the defendant ordered the plaintiff to complete the construction work in the amount of KRW 37,50,000,000,000, under the contract for C Model E, the first and second construction sites, and the glass Corporation (hereinafter “instant construction”) around July 2015. The plaintiff was paid KRW 10,000,000 from the defendant on July 10, 2018.
According to the above facts of recognition, the defendant is obligated to pay to the plaintiff the remainder of the construction cost of KRW 27.5 million and damages for delay.
2. The Defendant’s assertion argues that the Plaintiff agreed to reduce the price of the instant construction to KRW 23 million, and according to the statement in the evidence No. 3, it may be acknowledged that there was an agreement on reduction as alleged by the Defendant (hereinafter “instant agreement”). However, the content of the said agreement is to deposit KRW 10 million by July 10, 2018 and KRW 13 million by August 20, 2018, and the agreement shall be null and void if it is not paid within the said period. The Defendant is a person who has not yet paid KRW 13 million until August 20, 2018.
Therefore, the defendant's above assertion is without merit.
3. According to the conclusion, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 15% per annum from May 29, 2018 to the date of full payment, which is clear that the original copy of the instant payment order was served on the Defendant.
The plaintiff's claim is reasonable, and it is so decided as per Disposition.