(영문) 대구고등법원 2014.10.23 2013나6507
용역대금
Text

1. The plaintiff's appeal is dismissed.

2. The costs of appeal shall be borne by the Plaintiff.

Purport of claim and appeal

The first instance court.

Reasons

1. Basic facts

A. On February 13, 2009, the Defendant entered into a service contract for the entrusted development of a house development project (hereinafter “instant service contract”) with the Plaintiff to develop and sell a large number of lots of land (5,515 square meters), such as Gyeong-gun, Chungcheongnam-gun, Chungcheongnam-gun, etc. (hereinafter “instant project”) as a site for electric source housing, and the main contents thereof are as follows.

(A) “A” refers to the Defendant, and “B” refers to the Plaintiff. At that time, D, who was the representative director of the Plaintiff, drafted a service contract in the name of the Plaintiff: The contract period from February 16, 2009 to February 16, 2010: Article 2 [Scope of Services]

1. Authorization, permission, consultation and consultation in accordance with district unit planning;

2. Analysis of balance of projects based on development costs;

3. Agency for vicarious performance of responsibility (project operator, design change, and occasional report and consultation on a development plan);

4. Sales agency (including terms and conditions of E members treatment or special members) Article 3 / [Performance Terms and Conditions]

1. 1) Matters to be implemented in the project section A: 2) Cooperation and support for the affairs of authorization and permission 3) support for the affairs of sale in lots;

2.(1) Matters to be implemented “B” : (2) Matters to be considered to minimize project costs; (3) matters to be supplied to the project implementer in writing after the development of the standards of 30 households; and (4) matters to be supplied to the project implementer under the conditions of membership after the development of the standards of 4,000,000 won for the payment of KRW 4,00 to the project implementer 30; (4) matters to be supplied to the project implementer ; (3) matters to be supplied to the project implementer ; (4) matters to be supplied to the project implementer ; and (4) matters to be supplied to the project implementer ; and (4) matters to be supplied to the project implementer ; and (4) matters to be supplied to the project cost

1. “B” shall cover the consulting expenses referred to in paragraphs (1), (2) and (3) out of the scope of services referred to in Article 2 with 50,000,000 won, and the fees for sales by proxy referred to in paragraph (4) shall be 6,000,000 won per 30 households.