(영문) 대구지방법원 2017.03.09 2016고단5141
화재예방,소방시설설치ㆍ유지및안전관리에관한법률위반
Text

A defendant shall be punished by imprisonment for six months.

However, the execution of the above sentence shall be suspended for a period of two years from the date this judgment becomes final and conclusive.

Reasons

Punishment of the crime

The defendant is the owner of the Daegu Jung-gu C building, and the building is the neighboring residential facilities, which are specific fire-fighting objects.

An interested person of a specific fire-fighting object shall take necessary measures to install, maintain and manage fire-fighting systems ordered by the head of a fire station in accordance with the fire safety standards.

around November 30, 2015, the Defendant received an order for correction and supplementation on four occasions until December 30, 2016 from the fire station in Daegu, the head of the fire station in Daegu, receiving an order for corrective measures on December 30, 2015 from the fire station in Daegu, and failed to implement the order.

On July 8, 2016, at the defendant's house located in Daegu Suwon District Fire Station D around July 6, 2016, the defendant received the copies of the order to take measures (the fifth unit) inappropriate as a result of the self-inspection of the building in the name of the fire station in Daegu Jung-gu, Seoul on July 6, 2016, but failed to comply with the order by August 9, 2016, which was due date.

around November 30, 2015, the Defendant was issued a corrective order five times until July 8, 2016, such as receiving an order for corrective measures on December 30, 2015 from the fire station in Daegu, the head of the fire station in Daegu, and was issued a corrective order on December 30 of the same year.

On August 23, 2016, the Defendant received the Defendant’s house from the Defendant’s house located in Daegu Suwon District Fire Station on August 18, 2016, in the name of the chief of the fire station in Daegu, Daegu, on August 18, 2016, through the self-inspection of the building C building, but failed to comply with the order by September 20, 2016, which was due date, until September 20, 2016.

Summary of Evidence

"2016 Highest 5141"

1. Statement by the defendant in court;

1. C Building self-inspection: Notification of an order to take measures inappropriate (5j), the status of delivery of post offices registration, reporting on the results of on-site verification of an order to take measures (C building) as a result of a self-inspection, and "2016 Height 6140" certificate;

1. The defendant's person;

arrow