(영문) 서울중앙지방법원 2015.09.04 2014가합572586
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 220,00,000 as well as 20% per annum from January 21, 2015 to the day of full payment.

Reasons

The Defendant contracted on January 10, 2012, the construction of a new construction of a new construction of a future co-factory, Inc. 331-3, Echeon-si, Egycheon-si, Egycheon-si, Inc., the Plaintiff subcontracted to the Plaintiff on January 10, 2012, with the price of KRW 220,000,000, and the Plaintiff completed the construction in accordance with the said subcontract; the Defendant and the Plaintiff set the time for payment of the subcontract price after obtaining the loan after the completion of the entire construction; and the fact that at least three years have not yet passed since April 15, 2012, the scheduled date for completion of the construction was determined by

Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 20% per annum from January 21, 2015 to the day of full payment, as claimed by the Plaintiff, after a considerable period of time has elapsed from the completion date of the completion of the subcontracted construction cost of KRW 220,00,000, and after the completion date of the relevant completion date, as agreed by the Plaintiff.

Therefore, the plaintiff's claim is reasonable, and it is decided as per Disposition by admitting it.