1. The Defendant: (a) KRW 251,322,536 for the Plaintiff and KRW 5% per annum from January 31, 2012 to November 26, 2014; and (b).

Reasons

1. Basic facts

A. (1) On July 5, 200, the head of Gangdong-gu Seoul Metropolitan Government announced the decision of urban planning facilities (road) and cadastral approval to expand roads under the former Urban Planning Act (amended by Act No. 6655, Feb. 4, 2002) on July 5, 200. On December 11, 2000, the Defendant’s notification publicly announced the approval of the implementation plan for the above urban planning projects under Article 200-103 as the Defendant’s notification, which is the project implementer, as the project implementer. On April 2, 2001, the head of Gangdong-gu Seoul Metropolitan Government announced the change of urban planning facilities (road) and the approval of topographic drawings under the Defendant’s notification under Article 201-26, and on May 15, 2001, publicly announced the approval of the implementation plan for the urban planning projects (road change) to be constructed under the instant urban planning projects (road change).

(2) According to the instant urban planning project, the head of Gangdong-gu Seoul Metropolitan Government filed an application for the adjudication of expropriation of the land indicated below (hereinafter “instant land”) and the land indicated below B-9 square meters in Gangdong-gu Seoul Metropolitan Government pursuant to the instant urban planning project. On December 10, 2001, the local Land Tribunal of Seoul Metropolitan City rendered the adjudication of expropriation of the instant land and the instant land at KRW 103,90,950,00 in total, around December 10, 2001; and on January 2002, the head of Gangdong-gu District Court of Seoul, Seoul Metropolitan Government deposited the deposited amount of KRW 103,90,950 as the Plaintiff by designating the deposited person as the Plaintiff around January 284, 2002.

The land subject to compensation was transferred to Gangdong-gu Seoul Metropolitan Government on November 14, 2002 due to the change of land category and the merger on November 14, 2002, the Gangdong-gu Seoul Metropolitan Government 161㎡, and the administrative district was changed to 93m29,164,800 square meters on November 14, 2002, Gangdong-gu Seoul Gangdong-gu Seoul Metropolitan Government, which was relocated to G due to the change of land category and the merger on November 14, 2002, and thereafter the administrative district was changed to 631m2 in Gangdong-gu, Gangdong-gu, Seoul. (3) The defendant accepted the land of this case on January 31, 2002, and the acceptance on the above date on February 7, 2002.