(영문) 수원지방법원 2017.03.30 2015가단143474
건물등철거
Text

1. The Plaintiff:

A. Defendant B indicated in the attached Form No. 15, 16, 17, 18, 19, and 15, among the area of 258 square meters in Suwon-si E, Suwon-si.

Reasons

1. Determination on the cause of the claim

A. 1) The Plaintiff is deemed to have obtained the recognition of the Plaintiff’s land in Suwon-si E large 258 square meters (hereinafter “instant land”).

(2) As to the instant land, Defendant B is the owner of a building with a size of 14 square meters in the same order as indicated in the separate sheet No. 15, 16, 17, 18, 19, and 15, connected each point of which is indicated in the separate sheet No. 15, 16, 17, 18, 19, and 15.

3) Defendant C is the owner of a building with a size of 24 square meters on board, which connects each point of 11, 12, 13, 14, 15, 19, 20, 21, and 11 among the instant land, and is the owner of a building with a size of 24 square meters on board (c) part (c) part (c) of the instant land among the instant land. Defendant D is the owner of a building with a size of 17 square meters on board, which connects each point of 7, 8, 9, 10, 10, 11, 21, 20, and 7, of the instant land, and is the owner of a building with a size of 17 square meters on board

5) From November 16, 2015 to June 23, 2016, part of the instant land possessed by Defendant B among the instant land is KRW 305,340, and the land rent after June 24, 2016 is KRW 41,140, monthly; the land rent for the portion occupied by Defendant C from November 16, 2015 to June 23, 2016 is KRW 523,40, and the land rent for the period from June 24, 2016 is KRW 72,240, monthly; the land rent for the period from June 24, 2016 to June 23, 2016 includes the land rent for the period from June 16, 2015 to June 23, 2016; the land rent for the portion occupied by Defendant D, including the land rent for the overall period from November 16, 2015 to June 27, 2016.

B. According to the above facts of determination, the Plaintiff, the owner of the instant land, and ① Defendant B, among the instant land in his possession, remove and deliver a building of 14 square meters in part on the ship connected in order to each point of (b) of the attached drawing Nos. 15, 16, 17, 18, 19, 15, among the instant land, and land rent from November 16, 2015 to June 23, 2016, which is the date of the Plaintiff’s acquisition of ownership.