1. On June 19, 2015, among the Plaintiff’s conjunctive claim, the Defendant’s ancillary claim is Daejeon U.S. Seo-gu, the area of C used to the Partnership on June 19.

Reasons

Details of the disposition

Pursuant to Article 2 (2) and (3) of the former Act on Distribution and Price Stabilization of Agricultural and Fishery Products (amended by Act No. 6699, May 13, 2002; hereinafter “former Act on Distribution and Price Stabilization of Agricultural and Fishery Products”), the establishment of standards for the allocation of the area for the use of facilities is a “central wholesale market” established in the Seongdong-gu Nowon-gu, Daejeon Metropolitan City in July 2001, and the Plaintiff and B Association (hereinafter “B Association”) are wholesale market corporations designated by Article 2 (7) of the former Act on Distribution and Price Stabilization of Agricultural and Fishery Products.

According to Article 6 (1) and attached Table 3 of the Daejeon Metropolitan City Ordinance on the Management and Operation of Agricultural and Fishery Products Wholesale Market, two wholesale market corporations may be established in Category D of the wholesale market in this case, and only the Plaintiff and B Cooperatives shall be designated as a wholesale market corporation of Category D from the time of the establishment of the wholesale market in this case.

At the time of opening the wholesale market of this case, the Plaintiff and B agreed to distribute the area as follows, but on October 26, 200, the Plaintiff and B agreed to distribute the area as follows.

Matters concerning implementation agreements between corporations;

7. Adjustment of areas used for facilities at intervals of three years according to the results of the evaluation of wholesale market corporations pursuant to Article 77 of the Act on Distribution and Price Stabilization of Agricultural and Fishery Products;

Main Facility Area Allocation - Adjustment of Major Facility Area Allocation - Plaintiff: Priority, B: 4207 420 2,357 (67.8%) 2,074 (32.2%) 6,431 3,507 (55%) 4,878 4,878 3,60 4,878 4,878 2,478 2,478 2,478 2,40 2,40297 420 297 420 297 297 297 297/123/5 123/5 2928 2,250 250 2,25130 1,251,251,250 203, 201, 325, 201, 25, 301, 25, 2015 2, 25, 201,