logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울행정법원 2019.02.20 2018구단57868
손실보상금
Text

1. The defendant's 25,752,850 won for plaintiffs A, B, C, and D, and 57,494,290 won for plaintiffs E and each of them.

Reasons

1. Details, etc. of ruling;

(a) Project approval and public announcement, etc. - Project name: F Housing redevelopment and rearrangement project - Project implementer: Defendant - Project approval: G public announcement of Eunpyeong-gu Seoul Metropolitan Government on April 4, 2013;

B. The subject matter of expropriation made on May 26, 2017 by the local Land Tribunal of Seoul Special Metropolitan City: ① the 435 square meters (hereinafter “Hdong”) and its ground before Eunpyeong-gu Seoul Metropolitan City Hdong (hereinafter “Hdong”) in which Plaintiff A, B, C, and D owned (hereinafter “Hdong 1”), and ② the 97 square meters (hereinafter “second-party land”) and its ground obstacles before I owned by Plaintiff E, and the 97 square meters (hereinafter “second-party land”; when called together with land 1, “each of the instant lands” and “each of the instant lands”) were not claimed for the increased amount of compensation for each of the above obstacles, so the parts on each of the above obstacles are not separately indicated.

This provision shall also apply to compensation for losses by the ruling below.

① Plaintiff A, B, C, and D each 600,074,860 won [=Additional dues of delay (35 days from November 1, 2016 to December 5, 2016) of KRW 591,561,930 of shares 1/4 of land owned by Plaintiff A” [the delayed period of November 1, 2016 to KRW 35 days) 8,512,930], ② Plaintiff E 501,974,670 [the amount of KRW 501,974,670 of [the amount of KRW 2] 494,85,00 of land (the amount of KRW 8m2 of the land owned by Nonparty 2 shall be considered as “electric” and the remaining amount of KRW 9m2 of

() Delay additional charges (the delay period shall be 35 days from November 1, 2016 to December 5, 2016) - The date of expropriation shall be 7,119,670 won): July 14, 2017 - The Land Appraisal CorporationJ and the Bank of Arbitration. K

(c) The Central Land Tribunal’s ruling on February 22, 2018 - The adjudication on compensation for losses: ① The amount of delayed payment of KRW 622,523,810 for the Plaintiff A, B, C, and D, respectively (=the amount of delayed payment of KRW 613,692,560 for the 1/4 equity interest in the land = the amount of 1/4 equity interest in the 1/4 equity interest, as

(2) Plaintiff E 520,736,860 won (=The current status assessment is the same as at the time of the ruling of expropriation)

The delay period is the same as that of the expropriation ruling.

7,385,710 won) - An appraisal corporation: L/WU, the fact that there is no dispute over the L/WU, and the case where there are evidence Nos. 1 and 2.

arrow