Text
The defendant's KRW 51,371,409 and KRW 50,878,656 among them shall be 10% per annum from June 28, 2019 to April 28, 2020.
Reasons
In full view of the purport of the entire arguments in the statement in Gap evidence Nos. 1 through 7, it can be recognized as the same facts as the statement in the attached sheet.
According to these facts, the Defendant is obligated to pay to the Plaintiff damages for delay at each rate of 51,371,409 won (=50,878,656 costs of legal procedure for subrogation) and 50,878,656 won of subrogated payment, which is the date of delivery of the original copy of the instant payment order, from June 28, 2019 to April 28, 2020, which is clear in the record that the date of delivery of the original copy of the instant payment order, is 10% per annum from June 28, 2019 to the date of full payment, and 12% per annum from the following day to the date of full payment.
Therefore, the plaintiff's claim of this case is justified and it is so decided as per Disposition.