Text
Defendant
A and D Co., Ltd. shall be punished by a fine of three million won, by a fine of two million won, by a fine of two million won, by Defendant E.
Reasons
Punishment of the crime
Defendant
D Co., Ltd. (hereinafter referred to as “D”) is a contractor who has received a subcontract from D with respect to the construction work, Defendant A is responsible for the process management and safety management of the said construction work; Defendant B is the manager of D; Defendant C is responsible for the safety management of the construction site; Defendant C is the manager of the said construction work; Defendant C is responsible for the safety management of the construction site; Defendant C is the manager of the said construction work; Defendant C is the head of the construction work who is responsible for the safety management of the construction site; Defendant C is the head of the said construction work; Defendant C is the head of the construction work responsible for the safety management of the construction site; Defendant F is the manager of the said D; Defendant F is the safety manager of the said construction site; Defendant F is the person who is responsible for the subcontracted construction work. Defendant EF’s representative director is the person who is the subcontractor.
1. Defendants A, B, C, and E were engaged in construction at the construction site above around 08:15 on July 18, 2015, and the construction of the sc beam was carried out by J. Accordingly, the construction contractor, having the characteristics of work carried out only by the accurate communication between the signal number and the scke articles, shall specifically prepare the procedures for the phased work to safely carry out the sc beam in order to prevent any error in the communication between the workers, and shall ensure that all the participants of the work prior to the work can communicate clearly with the signal number and the scke articles in accordance with the plan through the phased work training, etc., and after inspecting the completion and maintenance of the vertical degree of the sc beam installation of both the sc beam beam installation, sending the sc beam line above the sc beam, and have the scline removed only when both the scke and the scke are completely dismantled, and shall thoroughly perform safety-related work and safety-related work during the work.