Defendant shall be punished by a fine of 1.5 million won.
If the defendant does not pay the above fine, KRW 100,000.
Reasons
Punishment of the crime
Defendant
A is the owner of two buildings located in B and 10 lots of the petition-gu, Cheongju-si, and the owner of the building may not use or allow him to use the building unless he has obtained the approval for use from the permission-granting authority.
Nevertheless, around December 28, 2016, the Defendant completed construction (extension) with permission to extend the area of 72.18 square meters by connecting the petitioner B and 10 parcels, the Cheongju-si, the Cheongju-si, and completed construction with permission to use the area of 72.18 square meters. On January 2017, the Defendant stated the 72.18 square meters in the indictment for the extension of the 72.18 square meters to the lessee. However, even if based on the written accusation of the head of the Gu’s accusation concerning the instant case, the prior occupied area prior to the approval for use is specified as the extended area, and the Defendant also admitted that the building was leased to C including the extended area, and thus, it is assumed that the Defendant does not infringe the Defendant’s right to defense, ex officio,
It was leased to use it as a factory and used in advance.
Summary of Evidence
1. Partial statement of the defendant;
1. Examination protocol of the police suspect against the accused (examination of the identity of the accused and list of evidence No. 34);
1. The Defendant asserts that the facts charged in the instant case do not constitute a violation of the Building Act. However, according to the aforementioned evidence, around January 26, 2017, the Defendant drafted a lease contract between Cheongju-si, Cheongju-si, between Cheongju-si, between Cheong-si and Cheong-si, with the term of lease from March 6, 2017 to March 5, 2019, the extension work connecting the said two buildings had already been completed at the time, and immediately after the preparation of the above lease contract, C including the said extension portion from the Defendant.