(영문) 서울중앙지방법원 2019.06.26 2017가합557892
하자보수에 갈음하는 손해배상청구의 소
Text

1. The plaintiff's lawsuit against the defendant C is dismissed.

2. Defendant B Co., Ltd. shall be 429,924,495 won to the Plaintiff.

Reasons

1. Basic facts

A. 1) The Plaintiff is a party to the instant condominium building in Yeongdeungpo-gu, Suwon-si (hereinafter “instant condominium building”).

(2) Defendant B is an executor who constructed and sold the instant aggregate building, and Defendant C is a company that executed the instant aggregate building by being awarded a contract from Defendant B on April 25, 2013, for the construction of the instant aggregate building.

B. The instant aggregate building and the cost of repairing defects 1) Defendant C did not construct the part to be constructed in accordance with the design drawings while constructing the instant aggregate building, or constructed the said part differently from drawings or in bad faith. Accordingly, the manager of the instant aggregate building requested the Defendants to repair the defects, etc. on June 21, 2017. (2) Until now, the instant aggregate building has the same defects as indicated in the repair expense table by the defect list in attached Tables 1 and 2, and the repair cost is as indicated below in the following general notification of defect repair.

(2) In the case of an item in which there is no special assertion or no separate determination is made, the appraiser calculated the cost of repairing defects by reflecting the results of the correction or supplementation. [In the case of an item in which the appraiser’s correction or correction is made, the cost of repairing defects shall be calculated by reflecting the results of the correction or supplementation.” [the total cost of repairing defects] 1 year 2 and 5 years 2 and 4 years 5 years 2 and 5 years 2, 2507, 250 22,512, 987 84, 471, 3722, 980, 982, 142, 734, 915, 491, 8230, 740, 740, 615, 807, 807, 8718, 888, 964, 2686, 2984, 29636, 2865

C. 1 The Plaintiff, including the transfer of damage claim, shall be liable to the Defendants for three times from August 23, 2017 to January 23, 2019.