Text
1. The Defendant’s KRW 196,743,300 among the Plaintiff and KRW 105,00,000 among the Plaintiff, shall be KRW 91,743,300 from May 5, 2016.
Reasons
1. Basic facts
A. On March 10, 2015, the Plaintiff entered into a contract with C Co., Ltd. (hereinafter “C”) on the installation of electric treatment facilities for C2, C2, and C chip (chip). On the same day, the Plaintiff and the Defendant entered into a subcontract with respect to the manufacture and installation of “ALCHIP (AL) electric treatment facilities” (hereinafter “instant construction works”) during the said construction works with respect to the said construction works, as follows:
(hereinafter “instant subcontract”). Article 2. Details
1. CHIP washing water tank 3.5TON/HR 3SEH 2ST, H3 1ST;
2. Magal Mabs 3.5TON/HR 3SET H2ST, H3 1ST;
3. Cut 3.5TN/HR 3SET 2SET, H3 1SE
4. 3.5TON/HR 3SET H2ST, H3 1ST;
5. 5T/7.5T/15T/30T/40 T, respectively, 1 SE Storage Article H2 H2 40T, H330T
6. LOT for the transport of chips;
7. Article 3 above 20V 60V 60Hz 3, and Article 3 above 220V 60Hz 3 for the first generation of H2
1. Value of supply) 1: Value of value: 920,000,000 won: 92,000,000 won; and
2. Payment Terms 1) Payment Terms 1) Payment Terms 20% 184,000,000 won (Additional Tax), 3/16 performance guarantee insurance policy (10%) after receipt of the contract performance guarantee policy (10%) and advance payment performance guarantee policy (20%) payment 2) intermediate payment 368,00,000 won (Additional Tax), 30% of intermediate payment 276,000,000 won (Additional Tax No. 4 payment after completion of installation of 7/5 scheduled facilities) and 10% of the remainder 92,00,000,000 won (Additional Tax No. 10%) and 5/31 payment method after receipt of the defective performance guarantee policy (10%): Payment method after receipt of the notice for delay payment 30 days from the date of issuance of the tax invoice: Article 6:
1.B shall pay A the amount equivalent to 3/1000 of the price for delay per one day immediately after delay in the payment period of this Agreement without good cause.
2. The compensation for delay under paragraph (1) shall be paid in case where he inflicts a loss on Gap due to a lack of production performance due to the delay in the payment period of Eul;