logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원부천지원 2014.12.05 2012가합9590
공사대금
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On March 10, 201, the Plaintiff entered into a subcontract for the instant 1, 2, and 3 projects with the Defendant: (a) on March 10, 201, the Plaintiff entered into a subcontract for the instant 1,188,000 won (including value-added tax; hereinafter the same shall apply in this paragraph) for the electrical construction among the new construction of urban-type residential housing complex buildings outside Guro-gu Seoul, and two parcels of land (hereinafter “instant 1 project”); (b) on March 13, 2011, between March 13, 2011 and April 30, 201, the subcontract for the instant 68,392,200, and construction period from October 25, 201 to October 30, 2011, with respect to the new construction of an urban-type residential housing complex building (hereinafter “the instant 2 projects”); and (c) during the construction period from October 25, 2011 to October 13, 201, 201.

B. 1) The Plaintiff and the Defendant agreed on the amount of additional construction works on January 4, 2012, 87,921,470 won [value-added Tax (7,03,717 won)] separate from the value-added tax (7,03,717 won].

subsection of this subsection.

(2) Around June 5, 2012, the Plaintiff agreed on KRW 18,776,050 as additional construction cost of the instant secondary construction project, and KRW 21,010,50 as additional construction cost of the instant secondary construction project. (2) The Plaintiff completed the instant primary construction project.

C. On July 1, 2012, the Plaintiff submitted to the Defendant a letter of waiver that the Plaintiff would waive all rights to the instant 2 and 3 works, while failing to complete the instant 2 and 3 works, and on the same day, the Plaintiff and the Defendant agreed in relation to the instant 2 and 3 works (hereinafter “instant agreement”).

1. The Plaintiff’s part of the construction work from the date of concluding the contract to July 5, 2012 should be settled through the on-site inspection.

(Provided, That the unit price shall apply at the time of settlement of accounts).

arrow