logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대구지방법원 2017.08.17 2016가단1530
공사대금
Text

1. From January 26, 2016 to August 17, 2017, Defendant Jinsung Co., Ltd.: KRW 13,49,600 to the Plaintiff.

Reasons

1. Facts of recognition;

A. The construction of the Defendant Line Construction Co., Ltd. (hereinafter referred to as Defendant Line Construction Co., Ltd.) subcontracted the portion of the construction work out of the above construction to Defendant Jinsung Co., Ltd. (hereinafter referred to as Defendant Jinsung Co., Ltd.) as the original recipient of Cwale Construction located in Daegu-gu B.

B. On August 1, 2015, Defendant Jinsung subcontracted the part of the building outer walls, the AL Complex Construction Works and the Jinsung Construction Work (hereinafter referred to as the “instant construction”) among the subcontracted construction to the Plaintiff.

C. The Plaintiff from August 4, 2015 to the same year

9. By 20.20, the instant construction was executed.

The Plaintiff’s construction work of this case is KRW 58,446,00.

E. The Plaintiff’s construction cost of the instant case is KRW 10 million on September 2, 2015, and the same year

9. 25. 10 million won received respectively.

In addition, the sum of KRW 12,434,40, and KRW 3,522,500, and KRW 15,956,90, and KRW 12,500, and KRW 3,52,50,00, used for the instant construction, were borne by Defendant Jinsung on behalf of the Plaintiff

F. After the construction of the instant construction project, there was an additional defect in the roof of the annual president (gulll), which was pre-construction prior to the instant construction project. This is the cause of metal scrap scrap caused by cutting the pipes of various steel products in the process of performing the complex board, the cream works, and metal works, respectively.

For the repair of the above defects, a seal shall be affixed after melting the iron surface, and 1,839,000 won shall be required at the expense.

In addition, the completion of the construction in the instant case caused water leakage in the outer framework of the building due to the lack of the completion of the construction in order to repair the defects, it is necessary to perform the construction of de facto container after the removal of the re-construction and reconstruction, and 8,070,000 won is required at the cost.

[Grounds: Facts without dispute; entries in Gap2 through 5; the identity of appraiser D; the result of the appraisal of defects; the purport of the whole pleadings】

2. Determination as to the claim against Defendant Jinsung companies

arrow