Text
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Basic facts
A. The Plaintiff was awarded a subcontract for the construction of the conduits for the power supply facilities contracted by the Korea Electric Power Corporation (hereinafter “Korea Electric Power Corporation”) from the gold industry. In addition, the Plaintiff was awarded a subcontract for the construction of the conduits for the C Power Distribution System and the installation of the D Power Distribution System (hereinafter “B”) from each contractor for the construction of the C Electric Power Distribution System, the C Electric Power Distribution System installation work, the C Electric Power Distribution System installation work, the D Construction Work, the D Power Distribution System installation work, and each of the above construction works).
B. From April 9, 2012 to November 30, 2013, the Defendant served as a construction site manager at the Plaintiff Company and was in charge of managing each of the instant construction sites.
C. The C Corporation completed road packaging in a state where two re-scepts (175m x 20m x 100m x 1m x 20m x x 1m) are insufficient, unlike its original design drawings, at the time of the excavation of the pipeline, and the Plaintiff re-exploded the road packed on December 4, 2013 and reconstructed the said part.
D The Corporation removed the Electric Manle, which was originally installed on May 23, 2013 by the Plaintiff, and re-established it at a different location on December 13, 2013; (2) has been engaged in drilling up to the point not indicated in the original design drawings; and (3) on October 18, 2013, the Defendant made an order to pay the construction price to the Tae Mani Corporation (hereinafter referred to as the “Teo Mani Corporation”), a sub-project, a sub-project that performed an emergency restoration work for waterworks damaged by an accident in the course of the tamping construction work on November 19, 2013, without obtaining the Plaintiff’s approval; and (4) on October 18, 2013, the Defendant made payment to each of the Plaintiff Company, a sub-project that performed an emergency restoration work for waterworks damaged by an accident.
(e) The Corporation shall construct adjacent efficacys to the construction site by some transmission pipes.