logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원평택지원 2016.09.23 2015가단16557
손해배상(기)
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. The Human Human Entertainment Co., Ltd. (hereinafter “Human”) entered into a contract with two Young-gu Construction Co., Ltd. for the construction of 470-4 ground wave publishing complex (hereinafter “instant construction”) on the construction of spawn-dong 470-4 ground wave publishing complex (hereinafter “the instant construction”). Two Young-gu Construction again subcontracted the instant construction to A for civil engineering works during the instant construction, and to the construction of spawn-style and reinforced concrete to Co., Ltd. (hereinafter “spawn Construction”).

B. Since the suspension of construction of the instant construction, India concluded a contract on April 23, 2014 with Asan Comprehensive Development Co., Ltd. (hereinafter “Asan Comprehensive Development”), which is the remainder of the instant construction, for construction, electrical construction, and installation works (hereinafter “the remainder of the instant construction”). Asan Comprehensive Development awarded a subcontract for construction of mold and reinforced concrete among the remaining construction of the instant case, to the Defendant, and the Defendant re-subcontracted it to Asan Comprehensive Development.

C. On March 28, 2014, the Plaintiff entered into a contract with the Plaintiff to lease a system distribution box for temporary materials in the construction site of this case and install the construction site of this case. By May 2014, the Plaintiff assembled and set up an item distribution sheet (hereinafter “the temporary materials of this case”) on the third and second underground floors of the instant construction site and the second floors of this case until May 2014.

From September 2014, the instant corporation was practically suspended due to the aggravation of human rights’s financial standing, etc., and the Defendant also suspended construction around January 15, 2015 and completed the construction at the construction site of this case.

E. On the other hand, from January 17, 2015, water has leaked in the underground areas of the instant construction site from around January 17, 2015, the flood began due to the failure of water pumping devices, and the instant temporary materials were flooded together.

[Reasons for Recognition] There is no dispute between the parties.

arrow