(영문) 서울동부지방법원 2014.12.11 2013가합10213
용역대금
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

Basic Facts

The purpose of the service contract is to conclude the following contracts for the smooth progress of consulting and development services for the real estate of this case developed by the defendant, and to stipulate the overall matters and duties concerning the contract between the plaintiff and the defendant:

Article 1 (Contents 1) Business Name: (Business Name 2) Business Area of Seongdong-gu Do New Construction 2: Business Area of Seongdong-gu Seoul Metropolitan Government and five lots: 5,001.70m2 (1,513) (Scope of Services) Article 3 (Scope of Services) (Scope of Services) The details of Services to be provided to the defendant are as follows: (1) Review of development plans and direction-making plans by sector: (2) Development Plan for each land: Land Use Plan; (4) Development Plan for each traffic line plan; (5) Development Plan for each traffic line plan; (4) Development Plan for each facility installation; (5) Development Plan for each marketing project; and (6) General Planning/Implementation of Construction Project Plan; (7) Planning/Implementation of Construction Project Plan; and (7) General Planning/Implementation of Construction Project related to construction:

A. Construction project management (CM) and supervision;

(b) Execution;

c. Other services 9) General consultation 10) General consultation 11) and 4 (Services Fees and Payment Conditions, etc.) 10% of service costs within 7 days after the completion of the construction permission for the second progress payment 30% of the service costs within 7 days after the completion of the construction permission for the second part payment 30% of the service costs within 7 days after the completion of the 30% of the 30% of the service costs within 7 days after the completion of the 3-year progress payment for the third part payment.

1. The consulting service cost shall be an amount equivalent to 0.8% of the gross sales (118,659,723,000 won) (excluding value-added tax), and the terms and conditions of payment shall be as follows:

Article 5 (Cancellation and Termination)

2. The plaintiff shall select a group of construction companies with priority, and shall submit to the defendant a letter of intent to participate, including not less than 60% of the construction and sales responsibility for the subject matter of Article 1, within seven days, and the contract shall be automatically terminated if the contract is not fulfilled.

Provided, That where it is necessary to extend the period.