(영문) 서울동부지방법원 2017.02.09 2015고단3660
입찰방해
Text

Defendants shall be punished by imprisonment for six months.

However, with respect to the defendant B, C, and D, it shall be between two years from the date this judgment becomes final and conclusive.

Reasons

Punishment of the crime

Some of the facts charged were corrected ex officio to the extent that it does not impede the defendants' exercise of their right to defense.

Defendant

A shall be the vice president of K located in Songpa-gu Seoul District Court, from November 20, 2012 to January 22, 2014, and shall work as the director of the K Information Security Agency, and shall take overall charge of the operation of the L Center under the above headquarters and the affairs of “the selection of the operator of the L Center from January 2014 to January 2015.”

Defendant

B The general affairs of M&A, the executive affairs of M&A, and the defendant D were the head of M&A strategic business of M&A, and the defendants were in charge of the bidding related to the call center operation service business of M&A.

1. Defendant A

A. From January 2011 to December 2011, 2011, the company name was selected and operated as a service company by the Co., Ltd. (P at the time the company name was the company name) and was selected by the Co., Ltd. as the service company from January 201 to December 201, 201, the M Co., Ltd. was selected as a service company at a lower price than the O Co., Ltd. and was selected by the M Co., Ltd. as a service company in the bid for L Co., Ltd. from January 201 to December 2013, 201.

K has been in charge of the operation of the above L Center from 2012 to 2013.

The termination of the term of contract with the MUG shall be entrusted to the Seoul Metropolitan Government Public Procurement Service in order to select a general competitive bidding from 2014 to 2015, and on November 14, 2013, it requested the Seoul Local Public Procurement Service to procure "L center operation services".

Accordingly, the Seoul Regional Procurement Service published a written request for a tender notice and a service proposal in Q countries (www.g2b.go.go) after consultation with the K manager, and followed the procedures for the “tender for the selection of service providers of the K Center from 2014 to 2015.” The written request for the tender notice and the service proposal are “the method of contract”, “the method of contract is “general competition”, “the method of tender is a contract by general negotiation”, and “the selection of negotiation partners” is “the technology evaluation proposal (80%).