(영문) 대구지방법원상주지원 2019.09.19 2017가합5279
공사대금
Text

1. The Defendant’s KRW 24,371,067 as well as 6% per annum from September 10, 2015 to September 19, 2019 to the Plaintiff.

Reasons

1. Basic facts

A. A Co., Ltd. (hereinafter “A”) is a company that runs civil engineering and construction business as a business.

B. Around February 29, 2012, the Defendant issued a public notice of tender for the construction project on the 9.98km of the river and bridge for Eriwon 9.98km (hereinafter “instant construction project”). The public notice of tender is “a long-term contract under which the instant construction project is a party to a long-term continuing construction project and enters into an annual contract on the part of the successful tender price within the budget for each fiscal year after bidding in total within the scope of the budget for each fiscal year,” and the period of the construction project was stated as 24 months from the date of commencement.

C. A participated in the tender of the instant construction by submitting a tender document stating the bid amount of KRW 7,752,794,000, and the Defendant determined A as the successful bidder.

A The construction period from March 20, 2012 to December 31, 2012; the construction amount is KRW 2,00,000; the construction amount is KRW 2,00,000; the construction period is from February 7, 2013 to January 2, 2014; the construction amount is KRW 2,70,000; the construction amount is KRW 2,70,000; the construction period is from March 3, 2014 to KRW 30,00; the construction period is from March 4, 2014 to September 29, 2014 to KRW 1,30,000; and the construction period is from March 16, 2015 to KRW 30,00; and the construction period is from March 29, 2014 to KRW 1,300,00,000; and the construction amount is from March 16, 2015.

The main contents related to this case are as shown in attached Table 1 among the general conditions of the contract for local government construction (hereinafter referred to as "general conditions") included in the instant contract for construction work.

E. On December 31, 2014, the Defendant is likely to share the instant project with concrete hole, etc., because the weather of the machinery from the temperature to A is sharply clear and the weather of the field is repeated.