(영문) 서울행정법원 2016.12.08 2016구합67585
손실보상금
Text

1. The Defendant: (a) KRW 4,766,400 for each of the Plaintiff A and B, and KRW 5,428,80 for each of the Plaintiff C and D, and each of them on December 19, 2015.

Reasons

1. Details of ruling;

(a) Business approval and public notice - Business name: E-Housing redevelopment and rearrangement project (hereinafter “instant project”) - Project implementer: Defendant - Public notice of project implementation authorization on September 26, 2013: the Eunpyeong-gu Seoul Metropolitan Government public notice of project implementation authorization on September 26, 2013

B. Decision on expropriation made on October 30, 2015 - Expropriation date of the Seoul Regional Land Tribunal on December 18, 2015 - Land subject to expropriation: The location of the attached Table 1 attached hereto, each land indicated in the lot number column (hereinafter referred to as “instant land,” and the individual land shall be specified as the lot number): Compensation as indicated in attached Table 1.

C. The Central Land Tribunal’s ruling on May 26, 2016 - Compensation: The phrase “the result of appraisal” in the attached Table 1 attached Table 1 is as indicated respectively - An appraisal corporation: Samwon appraisal corporation; a stock company; a Alban appraisal corporation; a stock company; a Alban appraisal corporation (hereinafter referred to as “Objection”) (hereinafter referred to as “appraisals”); and the result of said appraisal / [based on recognition] without dispute; the statement in the attached Table 1, 2, 1, 2, 1, 2 (including each number), and 2 (including each number), and the purport of the entire pleadings.

2. The assertion and judgment

A. Even if the land category and actual use status of the Plaintiffs’ assertion are roads, the difference between the amount calculated three times the result of the court’s appraisal on the premise that the pertinent land is a site and the result of the said appraisal should be compensated in view of the fact that the owners of the land within the redevelopment project area share the project cost.

(b)as shown in Appendix 2 of the relevant statute.

C. 1) The instant land is located near the northwest of the Eunpyeong-gu Seoul Metropolitan Government, and the surrounding areas are mixed with main commercial use, detached houses, multi-household houses, and tenement houses.