(영문) 인천지방법원부천지원 2020.07.17 2019가단19971
손해배상(산)
Text

1. The Defendant’s KRW 31,275,620 as well as 5% per annum from July 15, 2017 to July 17, 2020 to the Plaintiff.

Reasons

1. Basic facts

A. The defendant is a company aimed at the inspection of PCB (PCB) circuit board in Bupyeong-si, Busan, and manufacturing business related to the above.

B. On February 17, 2016, the Plaintiff entered the Defendant Company and worked for three trillion two posts (09:00 to 21:00 a week, night 21:00 to 09:00) and inspected the circuit board performance using the SINK’s machine that inspects the PCB circuit board performance (hereinafter “instant machine”).

C. The instant machines functioned upon a red electric pressing and a yellow mortar on both sides of the machines, and circuit plates on the left side of the machines automatically put up on the presses of the machines and the presses on the presses of the machines and the presses on the presses of the machines.

As a result of a performance test, the circuit board which has been completed by the inspection is automatically missing from the right side.

As above, he was listed above.

The gap between the landed press board and the main body board of the machine may be omitted with equipment such as circuit plates or sirens being inspected.

In the bottom of the front part of the instant machine, there is a door that can cover the fallen goods, and in the case of hand or other objects by hand between the presses and the upper part of the machine, the machine operation stops by putting it down in the license.

On July 15, 2017, around 08:30, the Plaintiff opened the front section of the instant machine to take out the products and appliances separated from the inside of the instant machine, and taken out the products. However, other employees D knew of this, and operated the machine by subdividing the beginning pressing of the instant machine, and the Plaintiff’s her knick was put on the machine.

(hereinafter “instant accident”) e.

The Plaintiff suffered injuries by the instant accident, such as damage to the pressure trags to the right well and the water department, damage to the right well, damage to the right well, and the structural frame of the upper part of the aggregate, the right joints of the 2, and the steel frame of underwater water, etc.

[Ground of recognition] Facts without dispute, Gap's statements in Gap's 1 to 8 and 12, Eul's images in Eul's 1 to 5, witness E and D's testimony, as a whole.