(영문) 수원지방법원 2018.11.22 2017가합15013
하자보수에 갈음하는 손해배상청구 등
Text

1. The Plaintiff:

A. As for the construction of the Defendant Shee Co., Ltd, Defendant 275,332,378 and 201,00,000 among them, Defendant Shee Co., Ltd.

Reasons

1. Basic facts

A. Status 1 of the parties concerned) The plaintiff is the Hanam Hanam Hanam apartment, which is located in 821, Hanam-dong, Hanam-dong (hereinafter "the apartment of this case").

(1) The construction of 14 units and 777 units, and Defendant Shee Construction Co., Ltd. (hereinafter “Defendant Company”).

(3) On March 3, 2009, the Plaintiff and the Plaintiff (hereinafter “instant contract”).

(2) The Defendant Company entered into a contract with the Defendant Construction Mutual Aid Association (hereinafter “Defendant Mutual Aid Association”) on June 12, 2008 with respect to the defects arising from the design drawings of the instant apartment complex or the inspection of the inspection of the use during the warranty period, and entered into a contract with the Defendant Company to guarantee the Plaintiff’s obligation to the Plaintiff (hereinafter “instant warranty contract”).

According to the instant guarantee contract, the Defendant Union issued to the Defendant Company a warranty bond for each type of work as indicated below with the Plaintiff as the guaranty creditor.

Serial 1 1,060,530,960 1,138,437,460 from March 04, 2009 to October 04, 20103.03 (1 year), 4,630,613, 857, 753. 13. 63. 36. 13. 46. 25,203. 36. 13. 46. 46. 1,043. 1,043,8085 machinery and equipment 139,676,845,46. 13. 206. 3. 3. 46. 1,205,206. 3. 16. 3. 1,205,206. 13. 7. 1,209,46. 7. 1,2005

B. The claim for defective construction and repair of the apartment of this case.