(영문) 대구지방법원 2020.11.19 2020고단3250
개발제한구역의지정및관리에관한특별조치법위반
Text

A defendant shall be punished by imprisonment for six months.

However, the execution of the above punishment shall be suspended for one year from the date this judgment becomes final and conclusive.

Reasons

Punishment of the crime

【Criminal Power】 On July 8, 2013, the Defendant was issued a summary order of KRW 3 million as a violation of the Act on Special Measures for Designation and Management of Areas of Restricted Development by the Daegu District Court, and was sentenced to a fine of KRW 4 million by the same court on December 11, 2019.

【Criminal Facts】

1. No person who violates the Act on Special Measures for Designation and Management of Areas of Restricted Development (unauthorized development acts) shall construct buildings, change the purpose of use, install structures, change the form and quality of land, fell bamboo and trees, divide land, stockpile goods, etc. in areas of restricted development, and any person who intends to construct buildings or install structures prescribed by Presidential Decree and change the form and quality of land following such construction or installation shall obtain permission from the Special Self-Governing City

Nevertheless, the Defendant did not obtain permission from the competent authorities, and around March 2019, contained concrete packaging on the floor of Daegu Metropolitan City B owned by the Defendant, which is a development restriction zone, and on the scale of 162.56 cubic meters, 5.08 cubic meters, stored waste delivery block equivalent to waste delivery block in a size of 118 cubic meters.

As a result, the Defendant changed the form and quality of land and stockpiled goods without obtaining permission from the competent authorities.

2. Where the head of a Si/Gun/Gu finds any act of constructing a building, altering its use, installing a structure, changing the form and quality of land, etc. in a development restriction zone without obtaining permission, in violation of the Act on Special Measures for Designation and Management of Development Restriction Zones (the violation of an order for correction), he/she may order the relevant violator to suspend the construction, to remove, close, rebuild or relocate the buildings, structures, etc., or to take other necessary measures within a reasonable period

Nevertheless, the defendant around July 4, 2019.