logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 2020.12.22 2018가단536947
용역대금
Text

1. The Plaintiff, Defendant C, Defendant C, Defendant D, Defendant D, KRW 1,862,534, and each of the said money from March 5, 2019 to December 5, 2020.

Reasons

1. Basic facts

A. Conclusion of a provisional contract on the services of a rearrangement project and money loan 1) B between the Plaintiff and the Defendants, and the Housing Reconstruction Project Association Establishment Promotion Committee (hereinafter “instant promotion committee”).

() On January 24, 2014, the Plaintiff and the housing reconstruction improvement project (a total floor area of a building is 145,528 square meters) in Dong-gu E-dong, Suwon-gu, Suwon-si.

hereinafter referred to as “instant rearrangement project”

[2] The provisional contract for the service (hereinafter “instant provisional contract”)

(A) The main contents as follows (hereinafter “A”) are as follows, and “B” refer to the instant promotion committee, and “B”, respectively.

(1) Article 2(1) of the Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents, Gyeonggi-do Ordinance on the Maintenance and Improvement of Urban Areas and Residential Environments, regulations on the promotion of the promotion of housing reconstruction and improvement projects, and articles of association, etc. shall apply to the entrustment of the service under Article 3 to the service under Article 3 to the service under Article 3, and the service under Article 3, to the service under Article 3 (Scope of the service under Article 3, 1).

1. Vicarious execution of and support for all business affairs of the promotion committee;

2. Vicarious execution concerning the consents to partnership establishment and to rearrangement projects;

3. Vicarious execution of affairs concerning the application for authorization to establish an association;

4. Review on feasibility and preparation of an implementation plan for a rearrangement project;

5. Supports concerning the business to select the designer and work executor;

6. Vicarious execution of affairs concerning applications for authorization for project implementation;

7. Vicarious execution concerning the formulation of management and disposal plans;

8. Other expenses required by the promotion committee from among the affairs of the promotion committee. Article 4 (Bearing of Expenses) (1) The following expenses incurred in implementing any reconstruction and improvement project until the construction works are selected:

1. Expenses for lawsuits for various authorization and permission;

2. Operating expenses of the promotion committee and the partnership (for example), 10. Other matters.

arrow