(영문) 인천지방법원 2017.02.10 2016나2680
공사대금
Text

1. Of the judgment of the court of first instance, the part against the defendant in excess of the money ordered to be paid below shall be cancelled.

Reasons

1. Basic facts

A. On March 25, 2015, the Plaintiff engaged in interior construction business, etc. under the trade name C (former: D) concluded a construction contract (hereinafter “instant construction contract”) between the Defendant and the Plaintiff, on the ground of Kimpo-si, that the Plaintiff newly built the instant building on the second floor and the neighborhood living facilities (hereinafter “instant building”) and that the Defendant would receive construction cost of KRW 73,100,000 (including value-added tax, KRW 80,410,000) from the Defendant. The content of the instant construction contract is as follows.

Article 1: 2.34.34.25,100,000 on the date of the contract for non-fixed-term down payment, deposit with the Plaintiff’s passbook 28.736.20,000,000 on the date of the completion of the first middle-term payment, deposit with the Plaintiff’s passbook 34.34.25,10,000 on the date of the contract for the payment of the purchase price, the Plaintiff may explain the reasons for extension to the Defendant when it is impossible for the Plaintiff to complete the construction within the period due to a change in the time of the construction or any other cause not attributable to the Plaintiff. (i) The Plaintiff may request the extension of the construction period to the Defendant when it is impossible for the Plaintiff to complete the construction within the period.

Article 2 Section 2(2) shall be limited to one time and the plaintiff completes the construction of this building within a total of 90 days at the latest by the plaintiff. Article 8: 1) The construction of this building shall be conducted in accordance with the following specifications and contracts in respect of electricity and water, road settlement 2) civil engineering completion and authorization: The construction of this building shall be conducted in accordance with the following specifications and contracts. The division size non-high-end cement cement companies between cement companies and non-strings shall be painted; the wood sector shall be made of cement cement cement companies; the wood sector shall be made in the string of the stude, the string, the string of the string, the string of the string, the steel sector shall be 19, the high-water high-speed external wall r19, the roofr 11, the roofr 30 in total sturstcker straw, the interior of the construction of the string string, the outer string, and the air string.