logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 울산지방법원 2014.06.10 2013가단5410
지체상금 등
Text

1. From March 12, 2013 to June 2014, 2014, Defendant KM General Construction Co., Ltd.: (a) KRW 4,895,000 to the Plaintiff.

Reasons

1. Basic facts

A. As to the new construction of 15 households for studio-type multi-household houses owned by the Plaintiff (hereinafter “instant new construction”) in Ulsan-gu, Ulsan-gu (hereinafter “instant building”), the following contract was concluded on November 29, 201:

(2) From November 30, 201 to April 30, 2012, the sum of the construction cost under a contract with D in the name of the Plaintiff and Defendant B (trade name): (i) the construction cost of KRW 595,00,000, and the construction period of KRW 30,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000

(Execution by D) Construction cost directly operated by the owner of the building shall be KRW 15,00,000,000,000).

When it is impossible to complete the construction on the date stipulated in the contract due to a cause caused by a disaster, the compensation for delay equivalent to 1/1,000 of the construction cost shall be deducted at the time of the payment of the construction cost for each day of delay.

B. 45,00,000 won in the construction contract under the name of the Plaintiff and Defendant KM Comprehensive Construction Co., Ltd. (hereinafter “Defendant Company”).

B. Defendant B, on behalf of the Defendant Company, entered into the instant contract under the name of the Plaintiff and the Defendant Company, on behalf of the Defendant Company as a technical director or field director.

In addition, the construction implementation statement attached to the contract of this case is divided into the portion of the construction work of the defendant company and the portion of the project owner, and the portion of the project owner includes 17 million won, 5 million won, and 8750,000 won, for the portion of the construction work.

C. On September 7, 2012, the Plaintiff obtained approval for the use of the instant building from the Ulsan-gu office.

From November 30, 201 to October 18, 2012, the Plaintiff paid KRW 578,550,000 to Defendant B as the price for the new construction of this case.

On May 21, 2010, the Plaintiff was governed by the evidence No. 4-6 of May 21, 2012, May 21, 2012.

arrow