Text
1. The Defendant’s KRW 2,136,783,917 for the Plaintiff and KRW 6% per annum from December 14, 2016 to May 22, 2020.
Reasons
1. Facts of recognition;
A. On December 22, 2005, the Plaintiff entered into a contract for construction works under a long-term contract (hereinafter “instant contract for construction works”) with the Defendant, setting the total construction cost of KRW 82,692,50,000, and the total construction period of KRW 2,880 with respect to the instant construction works (hereinafter “instant construction works”).
Of the general conditions of the construction contract applicable to the instant construction contract (hereinafter “instant general conditions”), the parts related to the instant case are as shown in attached Table 1.
B. The instant construction contract was concluded by the method of a long-term continuing contract in the form of a long-term continuing contract and revised on January 2, 2009, following the conclusion of the five-dimensional continuing contract. The modified content is as follows.
차수 계약일 약정준공일 계약금액(원) 해당 차수 차수 공기 총괄 해당 차수 총괄 장기계속계약 1차 2005. 12. 22. 2006. 4. 22. 120일 2,880일 50,000,000 82,692,500,000 2차 2006. 2. 2006. 12. 21. 300일 - 1,500,000,000 - 합의 2006. 12. 19. - - - 1,440,000,000 81,962,100,000 3차 2007. 2. 2007. 12. 20. 300일 - 3,878,000,000 - 추가 2007. 12. 18. - - - 3,888,000,000 81,272,400,000 4차 2008. 1. 2008. 12. 18. 300일 - 4,942,300,000 - 추가 2008. 12. 18. 2008. 12. 28. 310일 5,964,000,000 85,431,000,000 계속비계약 5차 2008. 12. 29. 2014. 1. 26. 1850일 - 74,089,000,000 - 추가 2009. 12. 17. - 1850일 - 79,591,000,000 90,933,000,000 추가 2011. 9. 5. - - - 80,651,000,000 91,993,000,000 추가 2011. 12. 26. - - - 82,073,000,000 93,415,000,000 추가 2013. 12. 30. 2015. 12. 30. 2554일 3,584일 - - 추가 2014. 12. 22. - - - 86,469,000,000 97,811,000,000 추가 2015. 12. 28. - - - 88,608,000,000 99,950,000,000 추가 2016. 6. 23. 2016. 9. 30. 2652일 3,682일 94,622,000,000 105,964,000,000 추가 2016. 6. 27. - - - 97,170,800,000 108,512,800,000 추가 2016. 9. 28. - - - 97,171,300,000 108,513,300,000
C. The instant construction was completed on September 30, 2016, and the Plaintiff was from the Defendant on December 14, 2016.