(영문) 수원지방법원성남지원 2016.04.22 2015가합201271
부당이득금
Text

1. All of the plaintiffs' claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Basic facts

A. From 197 to 1998, the Special Act on the Acquisition of Land for Public Use and the Compensation for Loss (hereinafter “each of the instant lands”) was acquired through consultation with each of the following land (hereinafter “each of the instant lands”) in order to acquire the site for the instant road project from P 30 to 30.0,00,000 square meters, from 197 to 290,000,000 square meters, 196:30,000 square meters prior to Q 295,000,000 square meters, 29,000 square meters prior to 30,000,000,000 square meters for each of the instant lands, and 1,57,000 square meters for each of the instant lands, 1,579,000 square meters for each of the instant lands, and 1,57,000 square meters for each of the instant lands, 29,000 square meters for each of the instant lands.

B. On April 25, 2001, the Minister of Construction and Transportation, on which the Defendant’s housing site development project and each of the instant lands were executed, designated the Y, ZJ as a planned area for housing site development in the AA zone, and announced it to AB on April 30, 2001. On December 14, 2001, the Ministry of Construction and Transportation announced the AD, AE, AF, AF, AG, AG, AG, and CM as a publicly announced AC of the Ministry of Construction and Transportation on December 14, 2001, and succeeded to the rights and obligations of the AH, AH, AI, AJ, AJ, AK, AM area for housing site development, the planned area for housing site development in the AA zone, and the housing site development plan (the project operator was the Korea Land Corporation, and the Defendant was established on October 1, 2009.

AA district housing site development project (hereinafter referred to as “instant housing site development project”) on December 26, 2002 with the Ministry of Construction and Transportation’s announcement of the Ministry of Construction and Transportation on December 26, 2002, with respect to the area of 9,036,525 square meters in Y and Z.

The designation and alteration of a prearranged area for housing site development, approval and alteration of a housing site development plan, and implementation plans.