(영문) 서울중앙지방법원 2014.05.29 2013가합2332
매매대금반환 등
Text

1. The defendant shall pay to the plaintiff KRW 32,302,349,880 and KRW 3,477,00,000 among them, from May 27, 2008, and KRW 10,000,000.

Reasons

1. Basic facts

A. The Defendant’s housing site development project is implemented in South Yangyang-si. The Defendant’s housing site development project under the Housing Site Development Promotion Act (hereinafter “instant housing site development project”) with respect to the housing site development project of 5,091,574 square meters per day in the boundary of each area of Namyang-si, Namyang-si.

The development plan and implementation plan were approved on December 7, 2006 by the Ministry of Construction and Transportation No. 2006-514 of the Ministry of Construction and Transportation. 2) The contents of the development plan formulated by the Defendant regarding the housing site development project of this case are as follows.

As the main entry part of the site that the Plaintiff purchased, the basic direction-setting for the principle of the indemnity for the name of the site and the basic direction-setting for the division, the construction of the introduction function for the formation of the Grandmark (large-type sales facilities, department stores, discount stores, etc.) urban access part of the city (large-scale sales facilities, department stores, etc.) which is a relatively large lot in order to secure symbolicness and form a Grandmark, and create a small-scale lot in order to create a 800 square meters wide-scale road to create pleasant urban images by creating a heavy scale to meet the demand for substantial commercial space creation of a building on the roadside side of the main road in the site of the commercial site, streetside adjacent to the commercial site, which is located in a 1,000 square meters wide-scale to meet the demand for the creation of a pleasant urban image at the end of the commercial site, and to create a pedestrian-centered road-centered pedestrian-centered road-centered pedestrian-centered road-centered road-centered road-centered pedestrian environment to ensure the promotion of the commercial area.

B. On April 3, 2008, the Defendant, upon entering into a land purchase contract with the Plaintiff and the Defendant, announced that some of the land in accordance with the instant housing site development project is supplied for general competitive bidding.

Paragraph 6 of the above Supply Notice "10.10.1 other oil" means some of the commercial sites and parking lots in the Namyang-si District are supplied by the PF business, and the application for purchase is made for this reference.

The term "" is written as "."

2. The plaintiff is above.