(영문) 의정부지방법원고양지원 2019.01.25 2017가단76506
손해배상(기)
Text

1. The Plaintiff:

A. Defendant C Co., Ltd. and Defendant D Co., Ltd. jointly share KRW 54,543,807 and the aforementioned amount.

Reasons

1. Fact-finding;

A. The E building (hereinafter “instant building”) is a complex building for the purpose of traffic and sale culture of the seventh and fifth underground floors, which is a building with the first underground floor connected to the subwayF G station.

The above building is divided into shopping mall Dong and terminal Dong, and the H filmer had been operating from the fifth to the seventh floor above the ground of the shopping mall, and I had been preparing for the first to the fourth floor above the ground.

In addition, on the third above ground of terminal operation, the J was in operation from the first to the second above ground.

In addition, the underground floor of the above building is not divided into shopping mall Dong and terminal Dong, and the underground first floor was leased by K Co., Ltd. (hereinafter “K”) and had been performing the internal construction work to operate a crate, and the underground second floor was used as a parking lot from the third to the fifth underground floor.

B. Around February 2012, M Co., Ltd. (hereinafter “M”) acquired ownership and completed the registration of ownership transfer under the name of the said company on the 10th of the same month with trust of ownership to N Co., Ltd., and M entered into a contract with Defendant B Co., Ltd. (hereinafter “Defendant B”) on the 20th of the same month for the management of facilities (FM: FM) of the said building, and entrusts Defendant B with the management of facilities of the said building and completed the instant building on March 21, 2012.

6. 18. Operation has been initiated by transportation facilities, etc. after commencing the operation of the J.

C. On February 18, 2014, M determined that Defendant B continued the facility management by extending the contract period with Defendant B by February 19, 2015. The instant building is owned by the P Co., Ltd. (hereinafter “P”) that is the trust business entity of the fund managed by the O Co., Ltd. (hereinafter “O”) on March 12, 2014 and QA that is the O’s subsidiary company.