(영문) 광주고등법원(전주) 2016.04.07 2015나100735
구상금
Text

1. The part against the plaintiff corresponding to the money ordered to be paid under the judgment of the court of first instance shall be revoked.

The defendant.

Reasons

1. Basic facts

A. On December 30, 2008, the Defendant entered into a contract for road expansion works among B with Yangyang Construction Co., Ltd., a limited partnership company, and the Korea Land and Transport Management Office of the Korea Land and Transport. On March 26, 2012, the Plaintiff was awarded a subcontract from the Defendant for household facilities construction works necessary for construction of D to be built in the neighboring sea of 124m2 in the Jeonan-gun, Seoul Forest and fields (hereinafter “instant household facilities construction”).

B. On May 13, 2012, the Plaintiff leased a 13 sn beam beamer, a steel structure, to be installed in a bridge, including a driver, on May 13, 2012, the Plaintiff leased a 50 ton weighter of F.50 tons from E (hereinafter “instant weighter”).

C. Around May 12, 2012, G, an employee of the Plaintiff, was aware of the site director of the instant provisional facilities construction, requested the Defendant to perform the ground work necessary for the instant mid-term construction for the instant mid-term construction at H’s request. Accordingly, around May 12, 2012, the Defendant used a large scale of stone as required by H at the location where the instant mid-term equipment is to be installed, and then excavated a small scale of stone, and then performed the construction work for the ground.

At around 07:30 on May 13, 2012, I, a driver of the instant flag, arrived at the site of the instant provisional installation works, and checked the installation of a string engine at the location where G and H, and reinforced the part in which he did not partly fluorize with H by putting a stone in the vicinity of H, and then putting a alzinum board above miscellaneous stone, and installed the instant string engine using a gluor (land).

E. Since around 08:00 of the same day, I, using the instant devices, carried the beam and then cut it in a bridge. From around 08:00, I opened the first and second beam in a normal bridge, and then opened the beam with the third beam light around 08:30.