(영문) 부산지방법원 2021.01.15 2020고합482
배임수재
Text

1. Defendant A

(a) The defendant shall be punished by imprisonment with prison labor for ten months;

(b)Provided, That the above punishment shall be imposed for a period of two years from the date this judgment becomes final and conclusive.

Reasons

Punishment of the crime

Defendant

A from January 1, 2018, a person who works as the head of the construction team of "D Industrial Complex Creation Project" in Gangseo-gu Busan Metropolitan City, the head of the construction team of "D Industrial Complex Construction Project" in Gangseo-gu, Busan Metropolitan City. Defendant B is the representative of "F in charge of the construction equipment lending, soil and stone transportation, distribution, sale, etc.," and G is the representative of "H in charge of construction equipment leasing and soil and stone construction works, etc."

1. Defendant A

A. As the head of the above E (State), the Defendant had the authority to manage and supervise the overall construction site, approve the removal of earth and rocks and rocks at the construction site, select a transport company, etc., and thus, there was a duty to fairly and faithfully approve the removal or select a transport company for the benefit of the company with the care of a good manager.

Nevertheless, around June 25, 2018, the Defendant received a request from the representative B of the F Co., Ltd. F Co., Ltd. F Co., Ltd. F Co., Ltd. F Co., Ltd. to the effect that “The Defendant may enter into a continuous transport contract as a shipping company at the construction site of the D Industrial Complex Construction Project, and there is a difference in various conveniences for smooth work at the construction site.” In return, the Defendant received KRW 1,00,000 from the Defendant’s I Bank Account (J) on the same day, as well as received KRW 1,00,000 from March 20, 2018 to January 30, 2020, the Defendant acquired property or proprietary benefits equivalent to KRW 44,137,000 in total under the same name from March 20, 2018 to May 30, 202.

Accordingly, the defendant acquired property or property benefits in return for illegal solicitation in relation to his duties.

B. As the head of the construction team of the above E (State), the defendant is obligated to manage the construction site fairly and faithfully for the benefit of the company and to select the equipment leasing company, as the head of the construction team of the above E (State), since he has the authority to manage the overall construction site, supervise the business, and select the equipment leasing company.