(영문) 부산지방법원 2017.11.23 2016가단301390
구상금
Text

1. The Plaintiff:

A. 102,513,773 won for Defendant Daeung Construction Co., Ltd.;

B. The defendant Taekman case is 50,941.

Reasons

1. Facts of recognition;

A. As to the Plaintiff’s heavy type C passenger cars owned by the Plaintiff (hereinafter “Plaintiff”), the Defendant Samsung Fire and Marine Insurance Co., Ltd. (hereinafter “Defendant Samsung Fire”) is an insurer who entered into an integrated automobile insurance contract with respect to D passenger trucks owned by the Defendant (hereinafter “Defendant Samsung”) and the Defendant Taej Construction Co., Ltd. (hereinafter “Defendant Taej Construction”) subcontracted the construction of soundproof walls (hereinafter “instant construction”) from the Korea Land and Housing Corporation around September 27, 2010 from September 27, 2010 to January 19, 2012 from September 27, 2010 to January 19, 2012.

B. (1) On October 4, 2012, Defendant Grand Construction reported an implementation plan for road construction to a district district with the jurisdiction of the F Highway. The name of the construction project: The two direction period from 52km to 54km for the place where G soundproof walls were installed: the two direction period from October 8, 2012 to December 31, 2012 (0-18:00 to 00, 09: 00 to 17:00: 2 construction guidance signs, four traffic signs, four (100), four (100), three (3) (on night), 3 (on night), 3 (on night), 3 (on night), 3, 5-distance signalling at the site of the construction project: the details of the construction project on the expressway from October 8, 2012 to December 31, 2012: the details of the construction project on the expressway to prevent the point of five (5)-lane road construction at the site of the construction project.

C. The network H, around 17:49 on October 17, 2012, had been carrying network I, J, K, L, L, M, N,O, P, Q, Q, and R on the Plaintiff’s vehicle and proceeding one lane on the two-lane road at the point of 54 km away from the 54km away from the highway C, J, K, K, L, M, N, P, Q, Q, and R on the Plaintiff’s vehicle, while completing the construction of soundproof walls and conducting the work of recovering safety facilities, such as Rabcon.