Text
1. All of the plaintiff's claims are dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
In fact, the relevant plaintiff is a company established on May 17, 201 with its business purposes, such as the manufacture and sale of non-metallic metals, the collection and sale of scrap metal, etc.
Defendant B is the representative of “E” under the name of the personal business chain engaged in the electrical construction business, etc., Defendant C is the actual operator of the above E, and Defendant D is the employee in charge of electrical construction under the above E.
Around May 2012, the Defendants, who carried out electrical construction and fire accidents, concluded a contract with the Plaintiff for the construction of “electric power distribution team for the 30-mast electric power plant” (hereinafter “electric power distribution team for the 20-mast electric power plant”) and “electric power distribution team for the lustter” (hereinafter “the instant factory”) and the construction of the Plaintiff’s factory located in the Gyeongbuk-gun F (hereinafter “the instant factory”). From that time, Defendant D was the working-level manager, and completed the instant construction around July 2012.
On February 9, 2013, when the period of temporary closure was Saturday, a fire occurred inside the factory of this case (hereinafter “instant fire”). Accordingly, the Plaintiff suffered damages caused by fire, such as electric power distribution teams installed inside the factory building of this case, such as power distribution teams for house-proof devices.
At the time of the occurrence of the instant fire before and after the instant fire accident, the instant factory was established with the main power distribution team, quarterly power distribution team, interim power distribution team, etc. as well as the main power distribution team established by the Defendants at the time of the occurrence of the instant fire, and the electric power distribution team of the said factory at the time of the main power distribution team through the main power distribution team.
(2) The electricity was installed in a structure that is supplied in order with the power distribution team for the power generation and the power distribution team for the tidal sea in the middle power distribution team.
On the other hand, if the power distribution team for the said period, the power distribution team for the current period, and the power distribution team for the current sea route, and the source location servers in the middle line are operated under the upper limit, each of the above.