(영문) 서울중앙지방법원 2020.05.08 2018가단5115910
구상금
Text

1. The Defendants jointly and severally agreed with the Plaintiff KRW 18,722,469, and 5% per annum from May 18, 2018 to May 8, 2020.

Reasons

1. Basic facts

A. 1) D is a temporary building of sandd position panel structure between reinforced concrete buildings located in E in Pakistan (hereinafter “Plaintiff shop”).

Around August 29, 2013, the Plaintiff and the Plaintiff entered into a general fire insurance contract with the following terms: (a) around August 29, 2013: (b) from August 2013 to August 29, 2018, the purchase amount of the insurance (50,000,000 building; (c) movable property of KRW 50,000,000; (d) KRW 10,000,000,000; and (e) KRW 100,000,000,000,000,000, and KRW 100,000,000,000 per day for store shutdown damage; (b) from August 29, 2013, Defendant B leased 1, G on the ground of the Plaintiff’s adjacent to the Plaintiff’s store, and concluded the general fire insurance contract with 00,000,000 won per person, 10,00000,000.

B. On September 11, 2017, at around 04:07, the occurrence of a fire and the occurrence of a fire presumed to have been removed due to clothes damage from an electric cable sealed into the Defendant’s shop, and the adjacent Plaintiff’s store was burned (hereinafter “instant fire”).

2) Due to the instant fire, the Plaintiff’s store suffered damages equivalent to KRW 14,19,603 of the building’s damages, KRW 13,422,54 of the total damages of the household fixtures, KRW 173,604,417 of the movable property damages, KRW 2,177,549 of the total damages of the facility, and KRW 203,324,123 of the facility damages as indicated below.

C. As a result of the investigation of the fire of this case, the so-called "Yanju Police Station that investigated the fire of this case" shall be deemed to be the roof sand site board of the Plaintiff's store, after being integrated, as a result of the damage to the clothes of 2 cable connected to the Defendant store as a result of the execution of joint identification with the Gyeonggi Northern Regional Office, Fire Station, Electric Safety Corporation, and Electric Safety Corporation.