(영문) 대구지방법원 2017.08.11 2016구합21963
손실보상금
Text

1. The defendant shall pay to the plaintiffs each amount stated in the attached Table 1's "recognized amount" and its corresponding amount from January 13, 2016.

Reasons

1. Circumstances and results of appraisal of the ruling;

A. Project approval and announcement 1) On June 25, 2007, the Gyeongbuk-do Governor shall be the former Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents (amended by Act No. 8852, Feb. 29, 2008; hereinafter “Urban Improvement Act”).

) Pursuant to Article 4(3) of the Act, the CE District residential environment improvement project (hereinafter “instant project”) with respect to the CD-day CD 79,450 square meters in Yongcheon-si.

(2) On March 24, 2009, in accordance with Article 4(1) of the former Act on the Maintenance and Improvement of Urban Areas (amended by Act No. 9729, May 27, 2009), a resident public inspection and announcement was made on the alteration of the rearrangement zone, etc. of the project of this case (amended by Act No. 9729, May 27, 2009).

(3) On July 2, 2009, the Mayor/Do Governor changed the rearrangement zone to 87,084 square meters in Yongcheon-si, Seoul Special Metropolitan City. 4) The rearrangement zone of the instant project was changed to cI publicly notified on January 25, 2010, and was changed to 86,950 square meters in common, and publicly notified on December 31, 2012, and changed to cJ to 85,660.5 square meters in common, the rearrangement zone of the instant project was changed to cI to 87,084 square meters in common.

5) On February 6, 2013, the Youngcheon-si Mayor approved and publicly announced a project implementation plan for some of the instant project areas as follows (hereinafter referred to as the “instant first project zone”) to the CK publicly announced by Yongcheon-si.

1. Types and names of rearrangement projects: CE residential environment improvement projects;

2. Location and area of a rearrangement zone: 27,290.50 square meters in Yong-si.

3. Project operator: Defendant.

4. Period for implementing the rearrangement project: From the date of authorization for project implementation to 60 days;

5. Date of authorization for project implementation: December 31, 2012;

The Central Land Tribunal’s ruling on expropriation on November 19, 2015 - The date of commencement of expropriation: January 12, 2016 - Land and obstacles listed in the column for “subject matter of expropriation” listed in attached Table 1: hereinafter referred to as “each land and obstacles of this case.”