The plaintiff (appointed party)'s claim is dismissed.
Litigation costs shall be borne by the plaintiff (appointed party).
Reasons
Basic Facts
A. On April 5, 2013, with respect to the size of 730 square meters among B forest land B (hereinafter “instant forest”) in Osan-si, Osan-si, B, 2287 square meters (hereinafter “A”), a lease contract was concluded on April 5, 2013 with the lessor as C, Plaintiff (Appointed), E, F, G, H, and lessee (hereinafter “B”) as the Osan-si market, and the following lease agreements were concluded:
(hereinafter “instant lease agreement”). The Defendant installed Gu I facilities on a 730 square meters of the instant forest land among the forest land.
(hereinafter referred to as “facilities in this case”). The purpose of using the leased property under Article 1: The period of lease under Article 2 shall be from January 1, 2013 to December 31, 2015; the period of lease shall be from January 1 to December 31, 2015; the period of lease shall be from January 1 to December 31, 2015; and if a separate contract is not entered into, the rent shall be paid on an annual basis; the period of payment shall be determined by applying mutatis mutandis the Public Property and Commodity Management Act and the Ordinance on the Management of Osan City Public Property (the officially announced land x the occupied area x 0.05).
Provided, That when calculating a monthly, the number of days less than one month shall be calculated on a daily basis.
Article 4 (B) is responsible for the preservation and use of leased property with the care of the manager, and may implement the project for environmental improvement, etc. for the leased area with the approval of A.
Article 5 Section A does not raise any objection to the retention and management of the beginning cost together with this contract.
B. The rent that the Defendant paid to the lessor under the instant lease agreement is as follows.
From January 1, 2013 to December 31, 2013, 2013 to December 31, 2013 x 730 square meters x 0.05 1,930,850 x 0.05 x 1,930 m2 from January 1, 2014 to December 51, 2014 x 730 m20 m20 x 0.05 m2 x 1,930,850 m20 x 730 m2 from April 1, 2015 to December 31, 2015 x 730 m20 m205 x 051,930 m205 m2016. 1 to December 31, 2016 to x 54, 2017 x 73037.107 m201.7