Text
1. The defendant shall pay 50,483,500 won to the plaintiff and 20% per annum from August 26, 2014 to the day of complete payment.
Reasons
1. Facts of recognition and judgment
A. Comprehensively taking account of the overall purport of the arguments in Evidence A Nos. 1 and 2, the Plaintiff is a company that manufactures and processes agricultural products. The Defendant is a company that runs wholesale and retail business of agricultural products. The Plaintiff is the Defendant, the Plaintiff is a company that operates wholesale and retail business of agricultural products, the agricultural products equivalent to KRW 27,690,50 on June 2014, and the agricultural products equivalent to KRW 22,793,00 on July 2014.
B. Therefore, the Defendant is obligated to pay to the Plaintiff the sum totaling KRW 50,483,500 ( KRW 27,690,500) and damages for delay calculated at the rate of 20% per annum under the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings from August 26, 2014 to the day of full payment, following the day following the day on which a copy of the instant complaint is served.
2. In conclusion, the plaintiff's claim of this case is justified and it is so decided as per Disposition.