(영문) 부산지방법원 2015.06.30 2014가단72643
대여금
Text

1. The Defendant’s KRW 19,620,00 for the Plaintiff and KRW 5% per annum from May 2, 2015 to June 30, 2015.

Reasons

The plaintiff asserts that the plaintiff lent 20 million won to the defendant, and claimed 34.9% interest per annum from the day after the delivery date of a copy of the complaint of this case to the day of complete payment.

Comprehensively taking account of the purport of the entire arguments in Gap evidence Nos. 1 and 2, the plaintiff lent KRW 19,620,000 to the defendant around April 18, 2014.

The defendant is obligated to pay to the plaintiff 19,620,000 won and damages for delay at the rate of 5% per annum prescribed by the Civil Act from May 2, 2015 to June 30, 2015, which is the day following the delivery date of a copy of the complaint in this case, and 20% per annum prescribed by the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings from the next day to the day of full payment.

However, there is no evidence to acknowledge the claim for the principal and damages for delay exceeding the above scope of recognition, and the plaintiff's claim is rejected.

The plaintiff's claim of this case is justified within the scope of the above recognition, and the remaining claim is dismissed as it is without merit. It is so decided as per Disposition.